Bakwena will be undertaking the replacement of concrete slabs at all our toll plazas on the N1N4 toll road as part of our maintenance program. These concrete slabs are showing signs of wear due to heavy traffic volumes passing over them on a daily basis.
The replacement of concrete slabs started in June 2010. The work is being done by a SMME contractor. The lanes will be closed between 1 and 3 weeks on average, with the exception of the mainline plazas which could be longer.
The schedule for replacement is as follows:-
N1 North and South | N1 North and South | ||
---|---|---|---|
Carousel | June/July/Aug 2010 | Doornpoort | June/July 2011 |
Maubane | Aug/Sept 2010 | Dr Swanepoel | July/Aug 2011 |
Hammanskraal | Sept/Oct 2010 | Brits | Aug/Sept 2011 |
Wallmansthal | Jan/Feb 2011 | Marikana | Sept/Oct 2011 |
Murrayhill | June/July/Aug 2010 | Kroondal | Nov/Dec 2011 |
Pumulani | March/April 2011 | Swartruggens | Nov/Dec 2011 |
Zambezi | April/May 2011 | ||
Stormvoel | April/May 2011 |
We do not expect any major delays to the traffic, please be patient whilst we undertake this work.